EWP test and tag: what gets tagged and what gets inspected

Last reviewed 19 November 2026.

An elevating work platform (EWP: a scissor lift, boom lift or similar) is not tested and tagged as one item. Two separate regimes apply. The parts that plug into a socket outlet (the battery charger and its supply cord, and any extension lead used to charge the lift or to feed the outlet on the platform) go on the test and tag register: every 3 months on a construction site, otherwise at the interval for your work environment. The machine itself is plant and follows the EWP inspection regime: a check by the operator each shift, a routine inspection at least every 3 months, a periodic inspection at least once a year, and a major inspection after 10 years of service. Different people do each, and the records are kept in different places. The split, a worked example and a sheet to print are below.

Where these figures come from. Read on the review date: Safe Work Australia's Inspecting and maintaining elevating work platforms (guidance material, January 2021); WorkSafe Queensland's maintenance, inspection and repair of EWPs page and its testing and tagging page; SafeWork NSW's electrical practices on construction and demolition sites fact sheet; and Genie's operator's manual for the GS-30, GS-32, GS-46 and GS-47 scissor lifts (part no. 1270102GT, eighth edition, third printing, December 2017) as an example of what a manufacturer specifies. The Australian Standards themselves (AS/NZS 3760, AS/NZS 3012, AS 2550.10) are paid documents and are not quoted here.

The decision rule: which list does this part go on?

The charger appears on both lists for a reason. Safe Work Australia's guide lists "Battery charger" among the items to check in periodic and major inspections, as part of the machine. The supply cord that goes into the wall is plug-in electrical equipment, and that is what test and tag covers.

Test and tag: the plug-in parts

Genie's manual shows what these are on a typical battery scissor lift. It lists a "Battery charger (on battery side of machine)" that takes 85 to 264 V AC, says to "Connect the battery charger to a grounded, AC 3-wire electrical outlet only" and to "Inspect daily for damaged cords, cables and wires", and lists an "AC outlet in platform" as standard, labelled "Power to Platform". That platform outlet is fed by a lead plugged into the machine, so the lead goes on the register too.

Plug-in partConstruction siteOther workplaces
Charger supply cord (the plug end of the onboard charger)3 monthsYour environment's interval (see how often to test and tag)
Extension lead used for charging3 monthsYour environment's interval
Lead feeding the platform outlet ("power to platform")3 monthsYour environment's interval
Tools plugged into the platform outlet3 monthsYour environment's interval

The 3-month figure is AS/NZS 3012 as SafeWork NSW publishes it ("Portable equipment and flexible electrical cords (extension leads): 3 months") and WorkSafe Queensland ("Construction work – other equipment: 3 months"). Off a construction site, regulation 150 of the WHS Regulations requires plug-in equipment to be tested where it is used in a hostile operating environment; whether that covers your lift depends on where it works.

Three site rules from the SafeWork NSW fact sheet that catch EWP leads:

The RCD built into a platform outlet. Genie's manual lists a "GFCI outlet" (the US name for an RCD-protected outlet) on the platform. We found no regulator page that says which RCD schedule applies to an RCD that is part of an EWP. Our suggestion, not a rule: press its test button before each use, as for a portable RCD, and ask whoever does the periodic inspection to trip-time test it and put the result in the logbook. See RCD test records for what to write down.

EWP inspections: the machine

These come from the WHS Regulations' plant duties as Safe Work Australia explains them. At a minimum an EWP must be inspected "in accordance with the manufacturer's recommendations", or a competent person's if there are none, or "annually" if neither is reasonably practicable.

InspectionHow oftenWhoRecord
Pre-operationalStart of each shiftThe operator, familiar with that modelChecklist; WorkSafe Qld: keep 1 year
RoutineAt least every 3 months unless out of service, or as the manufacturer saysA trained competent personWritten report; life of the machine
Periodic (annual)At least annually unless the manufacturer says otherwise; often set by hours usedWorkSafe Qld: an engineering tradesperson independent of the EWP's operationWritten report; life of the machine
MajorAfter 10 years of service, then every 5 years (Safe Work Australia); sooner if the manufacturer says, after damage or modification, or when imported or recommissioned without recordsWorkSafe Qld: likely the manufacturer, an engineering tradesperson or a professional engineerReport of work done, methods used and qualifications

Two notes on the sources. Safe Work Australia's guide gives the 10 years then every 5; WorkSafe Queensland's page says the major inspection is due at the end of a 10-year design life and should follow AS 2550.10-2006, and Standards Australia's store now lists a 2025 edition of AS 2550.10 that we have not read. A specialist's blog in the top search results describes the cycle differently again, so go by the manufacturer's manual and your inspector where they differ. And WorkSafe Queensland says the annual inspector "must be someone who does not normally operate the EWP" and must have authority to withdraw it from service.

Safe Work Australia lists what each written report should include: the competent person's name, qualifications and signature, date and place, inspection type, manufacturer, model, serial number, hour meter reading, date of manufacture or commissioning, and rated capacity. Records "must be kept for the period that the EWP is used or until you relinquish control of the EWP", and go to the new owner if it is sold.

Worked example: one battery scissor lift on a fit-out

An illustration, not a real business. A shopfitter owns one battery scissor lift first put into service in April 2016, with an onboard charger and a platform outlet. From 2 March 2026 it is on a construction site. Its charger cord and two leads were last tested on 12 January 2026; its last periodic inspection was in May 2025.

ItemListIntervalNext due
Charger supply cordTest and tag3 months on site12 April 2026
Charging lead, 10 A, 1.5 mm², 20 mTest and tag3 months on site12 April 2026
Power-to-platform lead, 10 A, 1.5 mm², 20 mTest and tag3 months on site12 April 2026
Pre-operational checkEWP logbookEach shiftEvery working day
Routine inspectionEWP logbookAt most 3 months3 months after the last routine inspection
Periodic inspectionEWP logbookAt most 12 monthsMay 2026
Major inspectionEWP logbookAfter 10 years of serviceApril 2026: due now

What the example shows: the April retest of three leads is a routine visit from a tester, while the major inspection due the same month takes the lift out of service and is likely to need the manufacturer or an engineer. Book the major inspection first and do the test and tag when the lift comes back. And the two 20 m leads cannot be joined to reach the far end of the floor: 40 m is over the 35 m limit for 1.5 mm² at 10 A.

Hired EWPs

SafeWork NSW: for hire equipment, "inspection prior to each hire and testing at not greater than monthly intervals. If hire equipment remains on site, then table two applies." The hire company owns the inspection logbook and should hand you a machine with current inspections. On delivery, check the tag on the charger cord and any supplied leads, ask to see the logbook, and do the pre-operational check yourself each shift. Queensland places separate duties on hire companies; see WorkSafe Queensland's hiring electrical equipment page, linked from its testing and tagging page above.

Two lists: sheet to print

Use your browser's Print on this page; the navigation is left off.

☐Test and tag register (plug-in parts)
☐Charger supply cord tagged; date within the interval (3 months on construction).
☐Every lead used to charge or feed the platform tagged, heavy-duty, not green, within length limits.
☐Lift plugged into an RCD-protected supply; no household power boards.
☐Platform outlet RCD test button pressed before use; result of any trip-time test recorded.
☐Tools used from the platform tagged.
☐EWP inspection logbook (the machine)
☐Today's pre-operational check done and signed (controls, limits, alarms, emergency lowering, tyres, leaks, guard rails, gate, decals, batteries charged).
☐Last routine inspection less than 3 months ago, written report on file.
☐Last periodic inspection less than 12 months ago (or as the manufacturer says), by someone independent of operating it.
☐Years in service checked against the major inspection (10 years, then every 5, or the manufacturer's figure).
☐Operator's manual in the storage container on the machine.

Lift: ____________ Serial: ____________ Hours: ______ Checked by: ____________ Date: ________

Keeping the register on a phone

TagVault can hold the plug-in half: add the charger cord and each lead as an item with the lift's name in its location, and it schedules the retests for the environment you choose and shows what is overdue. It does not keep the EWP inspection logbook, the hour meter or the major inspection date, so keep those with the machine. It is optional; the sheet above does both halves on paper.

Get TagVault on Google Play

Questions

Does a scissor lift need to be tested and tagged?

Its charger cord and leads do. The machine gets EWP inspections instead.

How often is an EWP charger tested and tagged?

Every 3 months on a construction site; otherwise at the interval for your work environment.

Who can do the EWP inspections?

A trained worker for daily and routine checks; usually the manufacturer, an engineering tradesperson or an engineer for annual and major inspections (WorkSafe Queensland).

Is the 10-year major inspection the same as test and tag?

No. It is a strip-down of the machine. Test and tag of the leads carries on separately.

What about insulated EWPs used near power lines?

They have their own dielectric testing by a specialist laboratory. That is not test and tag.

When this page does not apply

TagVault keeps records to support your test and tag program. It does not confer competency or licensing, inspect plant, or determine whether you meet any legal obligation. The quotations above are from the regulator pages and the manufacturer's manual linked, read on the review date; the Australian Standards and your EWP's manual are the authority. The shopfitter in the example is illustrative.