Test and tag requirements on construction sites
Last reviewed 18 November 2026.
On an Australian construction or demolition site, plug-in electrical gear follows AS/NZS 3012 (Electrical installations: construction and demolition sites), not the ordinary workplace schedule. In short: power tools, leads and portable outlet boards are inspected, tested and tagged every 3 months; fixed and transportable equipment and site sheds every 6 months; portable RCDs (safety switches) get a push-button test before each use and a timed trip test every 3 months. A competent person can test the tools and leads; the site wiring and switchboards need a licensed electrician. Each item carries a tag with the test date and the next due date, and the register stays on site for the length of the job. The full schedule, a worked example and a checklist to print are below.
Why construction is different
In most workplaces the duty to test comes from regulation 150 of the WHS Regulations and the interval comes from AS/NZS 3760 (see how often to test and tag). Construction work has its own regulation. NT WorkSafe puts it this way: "Regulation 163 of the WHS (NUL) Regulations requires electrical installations at a construction site to comply with Australian Standard AS/NZS 3012." SafeWork NSW calls AS/NZS 3012:2019 "a mandatory standard" under section 163 of its WHS Regulation 2025. WorkSafe WA's code says a business carrying out construction work "must comply with AS/NZS 3012:2010" under regulation 163.
So AS/NZS 3012 sets how often and what records. AS/NZS 3760 still supplies how to test: SafeWork NSW says site tools and leads "must be tested and inspected according to the methods in AS/NZS 3760".
The schedule
This is Table two of the SafeWork NSW fact sheet ("Periodic verification intervals, AS/NZS 3012:2019"). The Queensland and NT pages linked above give the same figures for the rows they cover.
| What | How often | Who |
|---|---|---|
| Construction wiring, including switchboards | Inspected and tested before it is energised, then visually re-inspected every 6 months | Licensed electrician |
| Relocatable structures (site sheds), fixed and transportable equipment | 6 months | Licensed electrician for transportable structures; competent person or electrician for other equipment |
| Portable equipment, flexible cords and extension leads | 3 months | Competent person or electrician |
| Equipment in amenities and site offices (kettle, fridge, microwave, heater) | 3 months | Competent person or electrician |
| Portable RCD: push-button test | Before each use of the equipment | The user, once shown how |
| Portable RCD: operating time (trip time) test | 3 months | Competent person or electrician |
| Fixed RCD: push-button test | 1 month | The user, once shown how |
| Fixed RCD: operating time test | 12 months | Competent person or electrician |
| Hire equipment | On introduction to service, then the interval for its class above | See "Hire gear" below |
| New equipment | Inspected for obvious damage before first use, and tagged | Competent person |
Two details from the same fact sheet. The timed RCD test checks "the tripping time which should be less than 300ms". And the "Who" column is SafeWork NSW's: a competent person is one "trained in use of RCD testers and Portable Appliance Testers", and a worker can do the push-button test "after being instructed on how to do it". What makes a person competent is covered in test and tag requirements in Australia.
These are maximums. A principal contractor can set a shorter cycle in its site rules; where it does, the site rule wins.
What does not belong on site at all
From the SafeWork NSW fact sheet:
- Household power boards, double adaptors and piggyback plugs "are not allowed on construction and demolition sites". Use a portable socket-outlet assembly: a site board with its own RCD and overload protection, on a heavy-duty lead no longer than 2 metres.
- Light-duty or green leads. An extension lead must be heavy-duty sheathed, "not green in colour", with conductors of at least 1 mm².
- Leads that are too long. Maximum lengths, including leads joined together:
| Lead rating | Conductor size | Maximum length |
|---|---|---|
| 10 A | 1.0 mm² | 25 m |
| 10 A | 1.5 mm² | 35 m |
| 15/16 A | 1.5 mm² | 25 m |
| 15/16 A | 2.5 mm² | 40 m |
| 20 A | 2.5 mm² | 30 m |
| 20 A | 4.0 mm² | 50 m |
These are things to catch at the visual inspection, before the meter comes out.
What the tag must show
SafeWork NSW: equipment that passes, and equipment new to service, "must be fitted with a durable non-metallic tag that clearly states the date it was inspected and the next date of inspection. It should also include the name of the person that performed the verification and the standard it was tested to (AS/NZS 3760)."
Colours. The same fact sheet says "Colour coded tags for each period are optional." A site can still require one colour per quarter in its rules, so an out-of-date tag shows from a distance. The convention tag suppliers and trainers describe is red for December to February, green for March to May, blue for June to August and yellow for September to November (as listed by Test and Tag Training, read on the review date). We did not find that mapping on a regulator's page, so treat it as a site convention and confirm it at induction.
Failed items. Non-compliant equipment "must be withdrawn from service immediately and have an out-of-service tag attached to it warning against further use", and is retested and tagged again when it comes back from repair.
Is your workshop tag good on site?
Only for 3 months from the test date. NT WorkSafe's bulletin: where equipment "originally tagged for use in a workshop" is used on a construction site, "that expiry date changes to three months from the date of original inspection e.g., tested January 2011 with the expiry date of January 2012, once on-site expiry becomes March 2011."
Decision rule for anything you are about to load into the ute:
- Tested less than 3 months ago: it can go. Its site due date is the test date plus 3 months, whatever the tag says.
- Tested more than 3 months ago, or no tag: retest first.
- Brand new in the box: inspect it for damage and tag it before first use.
Worked example: a carpenter starting on a site on 2 March
A carpenter subcontracts to a builder and starts on Monday 2 March 2026. The plug-in gear on the ute, last tested in the workshop on 12 January 2026 with 6-month workshop tags:
| Item | Qty | Site interval | Next due on site |
|---|---|---|---|
| Corded tools (circular saw, drop saw, planer) | 3 | 3 months | 12 April 2026 |
| Battery chargers (the charger is the mains item; the cordless tool is not) | 2 | 3 months | 12 April 2026 |
| Extension leads, 10 A, 1.5 mm², 20 m | 3 | 3 months | 12 April 2026 |
| Portable socket-outlet assembly with RCD | 1 | 3 months, including the trip-time test; push-button before each use | 12 April 2026 |
| Household power board | 1 | Not allowed on site | Leave it at the workshop |
The tags say July, but on site all nine items fall due on 12 April, six weeks after the start. Over a full year on construction work that is 9 items × 4 rounds = 36 tests, against 18 on the 6-month workshop cycle. Two of the 20 m leads joined would make 40 m, over the 35 m limit for 1.5 mm² at 10 A, so these leads cannot be run end to end.
A simpler routine: retest everything in the first week of each quarter, so every item shares one date and, where the site uses colours, one colour.
Hire gear
SafeWork NSW: "For hire equipment, inspection prior to each hire and testing at not greater than monthly intervals. If hire equipment remains on site, then table two applies." In practice the hire company inspects before each hire and keeps its own tests current, and once the item is on your site it joins the site schedule: check its tag on arrival, add it to the register, and retest it at 3 or 6 months if it is still there. Queensland places separate duties on hire companies; see WorkSafe Queensland's page linked above.
Records to keep on site
SafeWork NSW: "Records of inspection and tests must be kept for the duration of the construction/demolition job" and be "available for inspection at all times":
- a register of all equipment;
- a record of formal inspections and tests;
- a repairs register and record of faulty equipment.
It adds that electronic records, "computer databases, excel spread sheets etc", are acceptable. NT WorkSafe lists what each entry holds: who tested, the test date, the expiry date, and faulty equipment with the repair or removal. The SafeWork NSW site checklist also expects RCD trip-time results in the register. A blank layout is on our register template page, and SafeWork NSW publishes its own (Template 8 in the Housing industry site safety pack).
Each business on site answers for the gear it brings. Have your register ready at induction; a principal contractor can refuse untagged items under its site rules.
Which edition applies in your state
| Regulator page read | What it says |
|---|---|
| SafeWork NSW fact sheet | AS/NZS 3012:2019, mandatory under section 163 of the WHS Regulation 2025 |
| WorkSafe Queensland | Construction work follows AS/NZS 3012 (it links the 2019 edition); 6 months for transportable structures, fixed and transportable equipment and construction wiring, 3 months for other equipment |
| NT WorkSafe bulletin (updated 27 August 2024) | Regulation 163 and Electrical Safety Regulations 2024 regs 104 to 107 require AS/NZS 3012; 3 months for portable equipment, monthly and yearly for fixed RCDs |
| WorkSafe WA code of practice | "must comply with AS/NZS 3012:2010" under regulation 163; no interval table of its own |
SafeWork NSW notes that where WHS laws name a standard "they generally refer to a particular version". The 3 and 6 month figures above are the same in every source we read. We did not read the Victorian, South Australian, Tasmanian or ACT construction guidance for this page; ask your regulator which edition it enforces.
Before you go through the gate: checklist to print
| ☐ | Check |
|---|---|
| ☐ | Every plug-in item, lead and charger has a tag with a test date less than 3 months old. |
| ☐ | The tag shows the next due date and who tested; the colour matches the site rule, if there is one. |
| ☐ | No household power boards, double adaptors or piggyback plugs. |
| ☐ | Leads are heavy-duty, not green, undamaged, and within the length limit for their size. |
| ☐ | Portable outlet board has its own RCD; RCD trip time tested within 3 months and recorded. |
| ☐ | Everyone using a portable RCD has been shown the push-button test and does it before each use. |
| ☐ | Register is with the gear (paper or phone): item, test date, result, tester, next due, repairs. |
| ☐ | Hire items: tag checked on arrival and added to the register. |
| ☐ | Out-of-service tags on hand; anything damaged is tagged out and removed, not left in the shed. |
| ☐ | Next quarterly retest date is in the diary before it falls due. |
Site: ____________________ Checked by: ____________ Date: ________
Keeping the 3-month cycle on a phone
TagVault has a construction environment setting that schedules every item on a site at 3 months from its last test and shows what is overdue; scanning and recording work without a signal. Its limits here: it puts fixed equipment and RCDs on the same 3-month date (earlier than the 6 and 12 months above, never later), and it does not prompt the daily or monthly push-button checks, so keep those on a sheet at the board. It is optional; the register template and the checklist above do the job on paper.
Questions
How often do you test and tag on a construction site?
Every 3 months for tools, leads and amenities equipment; every 6 months for site sheds and fixed and transportable equipment.
Who can test and tag on a construction site?
A competent person or a licensed electrician for tools, leads and portable RCDs. A licensed electrician for construction wiring, switchboards and transportable structures.
Is my workshop tag valid on a construction site?
For 3 months from the test date, whatever expiry is printed on it.
Are coloured test tags compulsory on construction sites?
SafeWork NSW says they are optional. A site can still require them; ask at induction.
Can I use a household power board on a construction site?
No. Use a portable socket-outlet assembly with its own RCD.
When this page does not apply
- Not construction work. A fit-out crew's workshop, a factory or a shop follows the ordinary schedule: see how often to test and tag and what counts as a hostile operating environment.
- Site wiring, switchboards and generators. That is electrical work under AS/NZS 3012 and AS/NZS 3000 for a licensed electrician; this page covers plug-in gear only.
- New Zealand. See test and tag requirements in NZ.
- Mines. WA's code lists separate WHS Mines Regulations; ask the mine's electrical supervisor.
- A site rule that is stricter than this page. Follow the site rule.
TagVault keeps records to support your test and tag program. It does not confer competency or licensing, and it does not determine whether you or your client meet any legal obligation. The quotations above are from the regulator pages linked, read on the review date; AS/NZS 3012 and AS/NZS 3760 themselves are the authority. The carpenter in the example is illustrative.